Downtown Lafayette's sidewalks are getting a facelift. Kind of an eventual holiday gift to pedestrians -once the dust from the demolition and construction has cleared-funded primarily from a Transportation for Livable Communities grant. Crews will commence beautification on the downtown streetscape that will include new landscaping and paver sidewalks along Mt. Diablo Boulevard from Oak Hill Road to Mountain View in sections. Phase One will start January 9, and is slated to run until January 30 from the Round Up to Postino on the south side of Mt. Diablo Boulevard. The entire project will create some challenges for drivers and pedestrians for approximately the next six months. C. Tyson
Streetscape schedule: Phase 1 - Round Up to Postino (South side of Mt. Diablo Blvd.) January 9 - 30 Phase 2 - Postino to Bank of the West January 20 - February 17 Phase 3 - Lafayette Circle to Happy Valley Rd. February 15 - March 19 Phase 4 - Happy Valley Road east to Baja Fresh March 14 - April 6 Phase 5 - Celia's east to Chevron Gas Station April 4 - May 1 Phase 6 - Happy Valley Road to CVS Pharmacy April 26 - May 22 Phase 7 - Remainder to be completed
Before you print this article, please remember that it will remain in our archive for you to visit anytime. download pdf (use the pdf document for best printing results!)