Published August 22nd, 2018
Fire Station 43: vertical movement at last
Photo Nick Marnell

Moraga-Orinda Fire District Chief Dave Winnacker updated the board Aug. 15 on the Orinda fire station progress.
"The last of the concrete was poured on Aug. 13," the chief said. Because of the size of the site, the presence of the concrete crews has been inhibiting the speed at which the framers could work, but as the concrete crews finish up, there will be noticeable vertical progress on the site, Winnacker said.
The first floor should be completed by the end of the third week of August, and the second floor should be in place by the end of the month, with trussing and roofing in September.



print story

Before you print this article, please remember that it will remain in our archive for you to visit anytime.
download pdf
(use the pdf document for best printing results!)
Comments
Send your comment to:
Reach the reporter at:

This article was published on Page A10:



Quick Links for LamorindaWeekly.com
Home
Archive
Advertise
send artwork to:
ads@lamorindaweekly.com
Classified ads
Lamorinda Service Directory
About us and How to Contact us
Submit
Letter to the Editor
Send stories or ideas to:
storydesk@lamorindaweekly.com
Send sports stories and photos to:
sportsdesk@lamorindaweekly.com
Subscribe to receive a delivered or mailed copy
Subscribe to receive storylinks by email
Content
Civic
Lafayette
Moraga
Orinda
MOFD
Life
Sports
Schools
Business
Food
Our Homes
Letters/Opinions
Calendar
Copyright Lamorinda Weekly, Moraga CA