School Street Feasibility, Concept Development, and Implementation Study moves forward

By Vera Kochan — Published November 11, 2026 · Page 4 · View as PDF · Civic · Moraga · Issue

Moraga’s Town Council approved a professional services agreement of an updated project budget during its Oct. 14 meeting to begin the School Street Feasibility, Concept Development, and Implementation Study.  

    The agreement was awarded to Kimley-Horn and Associates, Inc. for a total not to exceed $499,533.83. The funding comes from a 2023 $600,000 grant administered by the Metropolitan Transportation Commission (MTC) and removes the previously programmed Measure J funding.

    In 2010, the Town Council adopted the Moraga Center Specific Plan (MCSP) that included the School Street project. Public Works Director/Town Engineer Nate Levine’s staff report explains that “the project extends from Moraga Way to St. Mary’s Road. The Capital Improvement Program (CIP) identifies improvements to this collector street and regional trail corridor, including a continuous multi-use path, sidewalks, bicycle facilities, roadway realignment, and intersection improvements to better serve all users.”

    Additionally, “The study will evaluate whether and how the planned improvements can be implemented, including the effects on Moraga Center circulation, shopping center access, property requirements, utilities, and environmental resources.”

    The purpose of the study will be to identify existing conditions and constraints by reviewing available records, collecting traffic data, preparing a topographic survey with property and utility mapping, and identifying constraints affecting potential improvements.

    Examining concept alternatives and circulation will help in evaluating changes to traffic patterns and shopping center access while assessing safety, pedestrian and bicycle connectivity including key intersection operations.

    Property and agency coordination will involve discussions with property owners and stakeholders in order to develop planning-level right-of-way cost estimates. 

    A preliminary environmental assessment will identify environmental constraints, additional technical studies, and the environmental review and permitting requirements for future improvements.

     The final scope of the study will be to come up with a preferred concept and implementation plan which will include construction and related project cost estimates, an implementation and funding roadmap, and a final study report.

    Kimley-Horn expects the complete study to take up to 11 months while staff coordinates with MTC to extend the current March 31, 2027 grant completion deadline to accommodate the study schedule.